PERT also known as program evaluation and review technique and CPM critical path method, are project management methods which help in controlling, monitoring, and scheduling network of tasks which are interlinked as well as simultaneous tasks. Project evaluation and review technique and critical path method have some distinct differences since duration of tasks are calculated differently in the 2 techniques. CPM users presuppose the duration of each task is known; PERT on the other hand allows for variation and uncertainty in every task in the project Nevertheless, both techniques are strongly related (CPM can be assumed to be a sub category of PERT), and many tasks can be analyzed using either technique.
In essence 6 main steps can be used in a hospital, to achieve minimum cost and meet deadlines involved in complex hospital projects:
A situation where both PERT and CPM can be used simultaneously in a hospital is as shown below:
Hurry up! Limited time offer
Get
19%OFF
Use discount code
Activity. Description. Immediate Predecessor. Earliest Start. Latest Time(days) Finish Time(Days)
A. Select medical employees 6 9
B. Conduct site survey A 10. 10.
C. Buying hospital Equipment B 11 13
Benefit from Our Service: Save 25% Along with the first order offer - 15% discount, you save extra 10% since we provide 300 words/page instead of 275 words/page
D. Prepare the layout of building plans. B 12 13
E. All materials are transported to the site. A 18 18
Support staffs are interviewed. C, D, A 18 18
VIP services
Get
extended REVISION 2.00 USD
Get
SMS NOTIFICATIONS 3.00 USD
Get an order
Proofread by editor 3.99 USD
Get an order prepared
by Top 30 writers 4.80 USD
Get a full
PDF plagiarism report 5.99 USD
Get
VIP Support 9.99 USD
VIP SERVICES
PACKAGE
WITH 20% DISCOUNT 23.82 USD
G. Delivery of equipment after purchase. F, I, J 13 15
H.Build the hospital. B
The critical path of the above hospital project will be ACFJK which will take the longest time of 46 days. In case any of the projects in this path becomes delayed, the whole hospital project will be affected.
Try our
Top 30 writers
BENEFIT
from the incredible opportunity
at a very reasonable price
If the same data is used under PERT technique the outcome will be the same however the Gantt chart diagram will be as shown below.
PERT technique has several advantages such as: it assists planners to organize complex projects and help them to make the necessary changes incase unforeseen delays occur. It also provides an easy analysis of areas of a project which need improvement or more manpower.
PERT techniques are vital in showing how much work has been completed by clearly showing the overall progress of the project. Many professionals use them when writing reports or presentations.
Try our
VIP support
BENEFIT
from the incredible opportunity
at a very reasonable price
On the other hand PERT techniques have some weaknesses. Such as, projects estimates must be carried out even before the technique can be used. This method also doesn’t leave room for correlation between works being done. This technique is also tedious when it comes to making changes; it usually requires the planner to redraw everything. Another major weakness is that you cannot create multiple options of schedules on the same diagram.
CPM has in proved to be more popular among planners and over time it has undergone more improvements. One advantage is that this method shows visible dependencies among tasks which enable the planner to focus on critical path activities to avoid major delays of the project. It also enables managers to identify slack for each task, as well as earliest start time and latest finish time. This method is also very practical when the planner wants to reduce time taken by the project by enabling planners to overlap activities and do them simultaneously where possible.
Want an expert write a paper for you?
This technique has some disadvantages such as: the network drawn can be very large, extending to different pages especially in cases where the tasks involved in a project are numerous. Without software it could take even weeks to develop a network diagram especially in situations where changes have to be made to the original plan. Another major weakness of this technique is that it tends to misrepresent the relative elements in a project and thus tasks which are behind schedule tend to be overlooked.